Published 2026-11-18 · Cyclone Bolt
Giga Energy, a U.S. manufacturer and developer of modular AI data centers with factories in Houston and Long Beach, announced on November 17, 2026 a 10-year lease agreement worth about $1 billion with an undisclosed U.S.-based AI cloud provider for a 60-megawatt data center under development in Hunt County, Texas. Reuters reported the deal the same day. Much of the facility is being manufactured off-site and assembled in Hunt County, which changes how a bolting package is planned: the modules arrive built, and the site work that remains runs from anchor bolts in the foundations to the anchorage of the equipment around them.
What Giga Energy announced
The figures below come from the company's November 17, 2026 release and from Reuters:
- A lease agreement worth about $1 billion, described in the release headline as a 10-year term, with a U.S.-based AI cloud provider the company did not name.
- A 60-megawatt data center on an approximately 30-acre campus in Hunt County, Texas. The release says the campus will serve hyperscale and AI cloud customers.
- Giga Energy broke ground in July and will develop, own and operate the campus for the customer, according to the release.
- The campus is due to be ready for service in spring 2027. The release says the project will finish in under eight months, which it describes as less than half the time of a traditional build.
- Approximately 300 construction jobs during the build and 24 permanent full-time positions, with estimated annual salaries the company put at $116,000 to $180,000.
Brent Whitehead, president and co-founder of Giga Energy, said in the release: "We believe AI infrastructure should leave a community stronger than it found it."
The release describes the company as a U.S.-based manufacturer, developer and operator of modular AI data centers with factories in Long Beach and Houston. It says Giga Energy has delivered more than 7 gigawatts of electrical infrastructure and has more than 258.5 megawatts of critical IT capacity completed and under development.
Power and water, by the company's account
Giga Energy frames the project around priorities the release says Governor Greg Abbott has called for: data centers paying for their own power, using water-efficient cooling, and keeping infrastructure costs from being passed on to Texas residents. The release says a cornerstone of the project is an investment in new electrical infrastructure that taps underutilized capacity, designed so the facility does not draw on the distribution capacity that serves existing homes and businesses.
On water, the company says the data center uses a fully closed-loop cooling system rather than open-loop evaporative cooling, and that it operates independently of municipal and groundwater supplies. The only local water use will be for sinks and employee bathrooms, which the release puts on par with two homes a year. Interesting Engineering reported the same cooling and construction details on November 17, 2026, and noted that the company has not disclosed a specific tax revenue estimate beyond "millions" a year.
Factory-built modules and the GigaBase system
The release says the project is the official unveiling of the company's GigaBase system, which it describes as data centers engineered to address long construction timelines, heavy water consumption and pressure on local utilities. Under what the company calls a modular, factory-first construction model, much of the facility is manufactured off-site before final assembly in the community. The release says this shortens construction schedules, reduces truck traffic and minimizes disruption to local roads and housing. Reuters put the expected build time at less than eight months.
Where anchor bolts fit a modular data center
A factory-built data center moves a large share of the fabrication and fastening into a plant, but it does not remove the site. The modules still land on concrete, and the power and cooling equipment that serves them still has to be anchored, connected and supported. The categories of threaded products such a project typically involves:
- Foundations: anchor bolts and anchor rods cast into the slabs and piers that carry the modules, along with the pads for transformers, switchgear and cooling equipment. On a compressed schedule, these are among the first materials needed, because they are set before the concrete is placed.
- Module tie-down and structure: structural bolting where modules are joined to each other and to their foundations, and hardware for walkways, platforms and equipment supports.
- Cooling: a closed-loop system is a piped system. Flanged connections in this kind of service are commonly made up with stud bolts and heavy hex nuts to the grades the piping specification names, with threaded rod and hardware for pipe supports.
- Electrical: anchorage for the new electrical infrastructure the company describes, and hardware for bus, cable tray and conduit supports.
The schedule is the part that stands out. A build the company expects to finish in under eight months leaves little room for a missing size to hold up a pour or a set. Buyers on fast-track projects commonly order anchor bolts and foundation hardware early and in full, keep the coatings and grades consistent across every pad, and plan for the shorts, the small quantities of missing items that surface at the end of a job. The grades, dimensions, coatings and paperwork for each item come from the project specifications and the engineer of record, not from the supplier, and buyers on projects of this size commonly ask for material test reports and lot traceability with each shipment.
The pattern has a second implication for the domestic supply base. If more capacity is built the way Giga Energy describes, more of the fastening moves into the factories where the modules are built, and the site-side bolting shrinks to foundations, anchorage and connections. That changes the timing of fastener demand more than the total.
Where Cyclone Bolt fits
Cyclone Bolt is a Houston, Texas manufacturer of fasteners, threaded products and custom machined components, established in 2016. Cyclone is supplying several large data center builds in Texas and welcomes more, from full-build take-offs to the shorts at the end of a project. Product families include stud bolts, heavy hex nuts, hex bolts and cap screws, double-end and tap-end studs, washers and gaskets, and custom machined components. Cyclone's published certifications include AS9100D, AS9120B, ISO 9001:2015, API Spec Q1, API 20E and API 20F; see quality and certifications. This article reports on a public announcement and news coverage. It does not describe Cyclone's own work, and nothing here indicates any Cyclone involvement in the project covered.
To discuss a data center bolting package, from anchor bolts to flange studs, request a quote with your take-off, specifications and delivery dates.
Sources
- Giga Energy Inks 10-Year, $1B Lease on Project Marl, a 60MW AI Data Center in Hunt County, TX, Giga Energy via GlobeNewswire, 2026-11-17
- Giga Energy signs $1 billion lease for Texas AI data center with cloud provider, Reuters via SRN News, 2026-11-17
- Texas plans 60MW data center with closed-loop cooling and faster construction, Interesting Engineering, 2026-11-17